Mactan-Cebu runway closed for 5 hours daily starting Sept. 1

Date:

Share post:

GMR Megawide Cebu Airport Corp. (GMCAC), which is running the operations at MCIA, said Wednesday the MCIA runway will be closed for overlay works from 1:30 a.m. to 6:30 a.m. daily starting this Saturday.

GMCAC Corporate Communications junior manager Avigael Maningo said the Mactan-Cebu International Airport Authority (MCIAA) originally planned to close the runway for eight hours, but it has been reduced to five hours after taking into consideration the effect the closure will have on airline operations.

Department of Transportation (DOTr) Secretary Arthur Tugade has also rejected the initial plan and ordered MCIAA general manager Steve Dicdican to have the daily repair works reduced to less than eight hours so as not to further inconvenience the traveling public with more flight disruptions and delays.

Because of the three-week temporary closure, the GMCAC has also proposed for the immediate construction of a parallel emergency runway while the main runway is shut down for rehabilitation.

When this plan materializes, Maningo said the airport will then have two operational runways “to provide the flying public with the seamless first-class service” they deserve.

For affected flights, passengers are advised to get in touch with their respective airlines to check the adjustments of their schedules.

In view of the five-hour daily closure, Philippine Airlines has already rescheduled and cancelled several of its flights.

“We ask for the understanding of the travelling public and we sincerely apologize for any inconvenience these closures would cause,” Maningo said.

The GMCAC also assured that they are working hand in hand with the MCIAA, DOTr, and the Civil Aviation Authority of the Philippines to ensure that the rehabilitation of the MCIA runway will be completed on schedule. –PNA

RIZAL MEMORIAL COLLEGEspot_img

Related articles

Habagat Brings Rains Across Luzon, Visayas as Typhoon Kiyapo Moves Away

MANILA (July 26) – The southwest monsoon (Habagat) will continue to bring rains over parts of Luzon and...

Davao-Samal Bridge: Big promise, big funding gap, ticking clock

DAVAO CITY  (July 24)  — The promise is bold. The deadline is tight. And the biggest question now...

Marcos confirms Sept. 14, 2026 date for first BARMM parliamentary polls

DATU ODIN SINSUAT, MAGUINDANAO DEL NORTE  (July 24)  — President Ferdinand R. Marcos Jr. on Wednesday confirmed that...

Gov’t rolls out ₱3.4-B projects, aid package for BARMM communities

COTABATO CITY  (July 24)  — The national government has rolled out around ₱3.4 billion in projects and assistance...